Revisorerna i Frankrike sågar det franska kärnkraftsprogrammet rejält i en färsk rapport.
“The most worrying uncertainties relate to the delays in the design of the EPR2, the unknown on the cost of the first three pairs (of reactors) and the lack of funding for the programme”
The Court noted that EDF has still not provided a profitability forecast for the EPR2 programme, as recommended, which means financing remains unclear
These delays and uncertainties (which affect also the number of power plants to be built) reduce the visibility of which the actors of the sector need to engage in the industrial projects of this magnitude and obtain financing,” the report said. “
The accumulation of risks and constraints could lead to a failure of the EPR2 programme.”
at the planned Sizewell C project, “
delays are already accumulating, even before the investment decision has been taken”. The court recommended that EDF should not make a final investment decision on Sizewell C “before obtaining a significant reduction in sound financial exposure in Hinkey Point C”.
Och det bara fortsätter och fortsätter....
https://www.neimagazine.com/news/france ... e-hurdles/